Posted: Mon Jun 12, 2006 6:36 am
Here is a slightly enhanced version showing a possible rough design cross-section of the duct area... (I also posted this under the other thread, but I kinda wanna keep a record of things about my project all in one place, so I put it here too)
Other notes:
- Ceiling joist spacing is 24 OC where duct precludes placing a joist; this is more than enough since the joists are back-to-back 400S165 20 guage structural (thus it's an 'I' shaped member, which will help tremendously with it's self support (in combo with the recommended web and flange supports); the combined web is also as thick as a single 14 gauge joist)
- Note that to maintain a roughly 16 OC for the rest of the ceiling joists, AND to get a 24 OC spacing around the duct, some of the ceiling joists will be pretty off-center in relation to the floor joists; there was really no way to keep a 24 OC ceiling joist spacing, due to the spacing of the floor joists, so I decided on 16 OC (roughly, as best as possible).
- Between-joist blocking is planned over cross-bracing since there would be little room to do that once the outer-leaf sheetrock is placed, and it can't be done before the sheetrock; the solid blocking can't be 100 percent solid because of the notches required to clear the ceiling joists, so it will likely be either doubled 2-by-8's or perhaps sandwiched multi-layer plywood (angle metal might be used at notches); the solid blocking will be done BEFORE adding sheetrock, as there would be significantly too little depth if added afterward.
- Ceiling joists will be blocked on the bottom flanges, but cannot be blocked at upper flanges since the floor joists will be in the way; there is relatively little chance of torsional movement or web crippling since the joists are back-to-back and flanges will be supported at ends and at least every quarter of span; additionally, a steel straping could be setup as a 'guy wire' in some places (screwed to the bottom steel straping or adjacent joist bottom flange); moreover, there seems there will be no real top force to initiate twisting (unlike a floor joist), but a force pulling down from the bottom flange -- AND, they are only 4 inches high, but with 2 back-to-back members joined together, they will be 3.25 inches wide (thus, I ask you: how much twisting force will there be?... it's not at all like, say a 2x10, which only has a 1.5 inch flange, yet is 9.25 inches tall!).
thanx,
K
Other notes:
- Ceiling joist spacing is 24 OC where duct precludes placing a joist; this is more than enough since the joists are back-to-back 400S165 20 guage structural (thus it's an 'I' shaped member, which will help tremendously with it's self support (in combo with the recommended web and flange supports); the combined web is also as thick as a single 14 gauge joist)
- Note that to maintain a roughly 16 OC for the rest of the ceiling joists, AND to get a 24 OC spacing around the duct, some of the ceiling joists will be pretty off-center in relation to the floor joists; there was really no way to keep a 24 OC ceiling joist spacing, due to the spacing of the floor joists, so I decided on 16 OC (roughly, as best as possible).
- Between-joist blocking is planned over cross-bracing since there would be little room to do that once the outer-leaf sheetrock is placed, and it can't be done before the sheetrock; the solid blocking can't be 100 percent solid because of the notches required to clear the ceiling joists, so it will likely be either doubled 2-by-8's or perhaps sandwiched multi-layer plywood (angle metal might be used at notches); the solid blocking will be done BEFORE adding sheetrock, as there would be significantly too little depth if added afterward.
- Ceiling joists will be blocked on the bottom flanges, but cannot be blocked at upper flanges since the floor joists will be in the way; there is relatively little chance of torsional movement or web crippling since the joists are back-to-back and flanges will be supported at ends and at least every quarter of span; additionally, a steel straping could be setup as a 'guy wire' in some places (screwed to the bottom steel straping or adjacent joist bottom flange); moreover, there seems there will be no real top force to initiate twisting (unlike a floor joist), but a force pulling down from the bottom flange -- AND, they are only 4 inches high, but with 2 back-to-back members joined together, they will be 3.25 inches wide (thus, I ask you: how much twisting force will there be?... it's not at all like, say a 2x10, which only has a 1.5 inch flange, yet is 9.25 inches tall!).
thanx,
K