emergency drywall screw question

Post by aschatzb »

hello,

The guys installing the drywall used a full schedule of screws on the first layer, even though I told them otherwise.

Do we pull the screws and mud the holes? Or are we better off leaving the screws?

I need to tell them something by tomorrow morning... Any quick advice would be very welcome:)

thanks,

andrew
rod gervais
Senior Member
Posts: 1464
Joined: Wed Oct 08, 2003 1:48 am
Location: Central Village CT
Contact:

Post by rod gervais »

Leave the screws

Rod
Ignore the man behind the curtain........
knightfly
Senior Member
Posts: 6976
Joined: Sun Mar 16, 2003 11:11 am
Location: West Coast, USA

Post by knightfly »

Right; in fact, some local codes won't even LET you use half-schedule on ANY layer (Californicate :? )
Soooo, when a Musician dies, do they hear the white noise at the end of the tunnel??!? Hmmmm...
aschatzb
Posts: 95
Joined: Wed Dec 01, 2004 2:23 am
Location: Asheville, NC

screws

Post by aschatzb »

Thanks guys! that's a bit of a relief...

can't wait for this to be over with... talk about epic!